Step-by-Step: How to Build Your Own House on a Stand in Zimbabwe

Admin August 25, 2025

If you've bought a stand in Zimbabwe congratulations! Owning land is a major milestone. But the journey from bare ground to a completed home can feel overwhelming. Whether you're building in Ruwa, Glen View, Gweru, or Marondera, knowing the exact steps can save you time, money, and stress.

Here’s a clear, locally relevant guide to help you build your own house from foundation to finish the Zimbabwean way.

Step 1: Verify Stand Ownership and Title

Why it matters: Before anything else, ensure your stand is legally registered and has title deeds or valid allocation documents (for local authority or cooperative stands).

Actions:

Tip: Without legal proof of ownership, council won’t approve building plans.

Step 2: Engage Professionals to Create Building Plans

To move forward, you’ll need approved architectural drawings.

Actions:

  • Hire a registered architect or architectural technician
  • Design house plans within zoning and building line regulations
  • Include floor plans, elevations, site layout, and sanitation plans

Cost of full architectural plans in 2025:

  • US$300 – US$800, depending on house size and complexity.

Plans must be approved by the local council (e.g., Harare City Council, Chitungwiza Municipality, or RDCs).

Step 3: Get Building Plan Approval from Council

Why it matters: Without council approval, your house is technically illegal and uninsurable.

Actions:

  • Submit plans, land documents, and IDs
  • Pay council plan approval fees (usually 1–2% of project value)
  • Receive stamped Approved Building Plan

Timeline: Approval may take 2–6 weeks, depending on the local authority.

Step 4: Hire the Right Construction Team

You’ll need a reliable, experienced team to handle the build.

Required professionals:

  • Builder / Contractor
  • Engineer (especially for slab or two-storey structures)
  • Quantity Surveyor (optional but helpful for costing)

Avoid informal builders without contracts construction disputes are among the top property complaints in Zimbabwe.

Tip: Use a written contract that outlines scope, timelines, costs, and penalties.

Step 5: Create a Realistic Construction Budget

Building in stages? You still need to budget properly.

Approximate Building Costs in 2025:

House Type

Avg Cost (US$)

2-Bed (60–80sqm)

$18,000 – $28,000

3-Bed (100–120sqm)

$30,000 – $45,000

4-Bed (150+ sqm)

$45,000 – $70,000+

Budget includes:

  • Labour
  • Materials (cement, bricks, roofing)
  • Transport
  • Council inspections
  • Finishing (plumbing, tiling, electrical)

Add a 10–15% contingency for unexpected costs (e.g., price hikes, delays).

Step 6: Begin Construction (Foundation to Roof)

Key Construction Stages:

  1. Site Clearing & Pegging
  2. Excavation & Foundation
  3. Boxing, Steel & Concrete Slab
  4. Walling (Up to Lintel Level)
  5. Roofing
  6. Plumbing & Electrical First Fix
  7. Plastering & Screeding
  8. Painting, Tiling & Fittings
  9. Final Plumbing & Electrical Fix
  10. Cleaning & Finishing Touches

Average project timeline (for a 3-bed house):

  • 3–8 months, depending on cash flow and builder availability.

Tip: Build in phases if you’re funding with cash:

  • Phase 1: Foundation + slab
  • Phase 2: Walling + roofing
  • Phase 3: Finishes + fittings

Step 7: Pass Council Inspections

Most local councils require inspections at key stages:

  • Foundation
  • Slab
  • Roof
  • Completion

Actions:

  • Call inspectors at each stage
  • Get written reports or approvals
  • Fix any flagged issues before proceeding

Final occupation certificate is needed to officially live in or sell the property.

Step 8: Move In or Market the Property

Once the house is complete and compliant, you can:

  • Move in and enjoy your new home
  • Rent it out for income (avg rent for 3-bed in Harare West: US$350–$600/month)
  • Sell for a profit

According to Property.co.zw, homes built between 2020–2023 resold at 12–30% profit, especially in fast-growing zones like Ruwa and Zimre Park.

Keywords: new house Zimbabwe, selling built property, rental return Zimbabwe

Common Mistakes to Avoid

  • Starting construction without approved plans
  • Using cheap, substandard materials
  • Not signing a written agreement with your builder
  • Ignoring council inspections
  • Failing to budget for finishes (windows, tiles, paint)

Final Thoughts: Build With Vision and Discipline

Building a house on your stand in Zimbabwe is more than just bricks and mortar it’s a legacy. Whether it's your forever home, a rental investment, or a family inheritance, planning and budgeting every step ensures you don’t just build a house you build wisely.

Need Help With Plots, Builders or Plans?

Visit Property.co.zw to:

  • Find serviced stands ready for development
  • Browse affordable plots in your preferred city or town
  • Connect with registered contractors and architects
  • Access construction tips, cost calculators, and renovation guides

Build smarter with Zimbabwe’s No.1 Property Marketplace trusted by over 8,000 users daily.

Share this article

More Articles

Subscribe to our newsletter